City of Dunwoody
Home MenuMount Vernon Intersection & Path Phase 1
Mt Vernon Place to Jett Ferry Road
Current activities:
(February 2026) The invitation to bid is currently being advertised.
(Jan. 2026) Construction plans have been submitted to the utilities for final coordination before bidding in January.
(Oct. 2025) Coordinating final stormwater plans and utility relocations.
(Sept. 2025) City right-of-way acquisition phase is complete. Coordinating final stormwater plans and utility relocations.
(July 2025) Final plans are being updated to reflect final right of way agreements and utility relocations.
(May 2025) Agreements reached for all right-of-way and easements. We're currently waiting on one closing and Georgia Power easement acquisition before advertising a bid for construction.
(October 2024) Utility Relocations in progress
(September 2024) Right of way acquisition is ongoing.
(August 2024) Received utility relocation plans from all affected utilities. Right-of-way acquisition is ongoing.
(July 2024) Coordinating utility relocation plans with Georgia Power. Right of way acquisition is ongoing.
(June 2024) Coordinating utility relocation plans with Georgia Power, telecom companies and Atlanta Gas Light. Utility plans are due in June. Right of way acquisition is ongoing.
Project details:
This intersection has been identified in the City of Dunwoody’s Comprehensive Transportation Plan as a priority project due to its current poor safety and low level of service. This intersection and the surrounding corridors lack adequate turn lanes along Mount Vernon Road and have limited accommodation for non-motorized users. The goal of this project is to correct these deficiencies and improve the safety and operations of this intersection.
Plans have been developed for the Mount Vernon Road at Tilly Mill Road. The design for this intersection and the surrounding corridor includes the addition of left turn lanes on Mount Vernon Road at Tilly Mill Road and at other adjacent intersecting roads. These modifications will improve the level of service and reduce rear end collisions along the corridor by providing turning vehicles a place of refuge. It will also reduce the number of angle collisions at Tilly Mill Road by enforcing proper lane assignments though the intersection. The design also provides for improved pedestrian crossings as well as a multi modal path along the north side of Mt. Vernon Road.
