Current activities:
(May 2026) Join us for the official opening of the new facility on Thursday, May 21, from 4 to 6 p.m. We'll celebrate with a ribbon-cutting and Touch-a-Truck. Stop by, then stay and grab dinner at the new Dine Around Dunwoody, sponsored by the Dunwoody Homeowners Association.
(April 2026) Water, sewer, and power service lines were installed, site grading was completed, and curb installation and interior finishes on both buildings began.
(February 2026) Steel structure and roof completed for both buildings. Warehouse building completion scheduled for March.
(January 2026) The site retaining wall was completed. Most of site grading and stormwater system was completed. Footings were poured for warehouse building.
(October 2025) - The contractor mobilized and began building demolition.
(April 2025) - Dunwoody City Council approved the construction contract. Construction is expected to begin in Summer 2025 and be completed by Spring 2026.
(September 2024) - Proposals for a Construction Manager will be received. Construction is projected to begin in 2025.
Project details:
The new Brook Run Maintenance Facility will cover 8,400 square feet across two floors on the site of the current maintenance building on DeKalb Drive in Brook Run Park. The aging, existing brick structure will be torn down to create room for a new pre-engineered metal building and maintenance yard. The current facility predates the park and is not designed for the city’s current maintenance operations.
The new building will be located to maximize space for park and street maintenance equipment and materials. The new structure will contain loading docks, material storage, a workshop, and drive-in storage on the ground floor with offices and a conference room on the floor above. Best practices for stormwater storage and water quality treatment will be incorporated into the site plan.